Our contractor Downer will be doing the work in the Greta Point village in two sections starting at the northern end.
For the first three months, from late April 2025, we'll be working from where the new style walking and bike paths come to an end at the moment to just before the NIWA driveway. Traffic management will be in place extending about 50m further in both directions.
Once the new walking and bike paths on this section are in, work will happen between the NIWA driveway and Cog Park. Traffic management will be relocated around the new work zone. Work on this section will take another three months.
There will be a 30km/h speed limit in place around the work zone at all times. Stop/go traffic management will operate during work hours - generally 9am-4pm, Monday to Friday with traffic down to one lane. Where the existing path is out of action, there will be detours in place for people walking. People riding bikes will either need to stay in the traffic lane or get off and walk bikes through the pedestrian detour.
Until about August, there will be traffic management in place in two locations on Evans Bay Parade during work hours - at Hataitai beach and at Greta Point.
What to expect – north end of Greta Point (late-April to mid-to-late July 2025)
What to expect - south end of Greta Point to Cog Park (approximately mid-to-late July till about the end of October 2025)
What to expect - Hataitai beach
It’s expected work to complete the remaining new walking and bike paths from Cog Park to Cobham Drive will happen once the work at Greta Point is complete. We’ll provide more information when timing is confirmed.
In the meantime, the new bike and footpaths will be installed in the Hataitai beach area where work is under way to upgrade sea and retaining walls. Installing the new bike path and footpath means we can complete this area without needing to come back in the near future. This will also enable us to make use of the traffic management already in place and do all the planned work in the beach area at the same time over winter.
The work on the seawall was tricky at first as our contractors worked around the tides and some ground-related challenges, but it is going well and on schedule. Weather permitting, work in the beach area, including the new paths, is expected to be complete in August.
This will include:
slightly raising the pedestrian crossing
work on the hillside of the road to install two P10 parking spaces.
Work on the wall at the rear of the beach started in mid-April following the completion of the new wall to the south of the changing rooms.
You’ll still be able to swim, and use part of the beach at all times. The changing rooms and toilets are open as usual.
In line with the approved plans for this area, some of the parking that has been out of action during construction will not be reinstated. The bus stops just east of Hataitai beach (city-bound stop 7549 and eastbound stop 6549) will be permanently removed once the paths are complete – watch for Metlink updates about this. The bus stops at Cog Park will remain and provide easy access to the beach.