Construction update

September 2024

Thorndon Quay has been divided into 13 areas for construction. We will generally be working in two areas at any given time.A map of Thorndon Quay showing that it is divided into 13 areas.

Area 1 - Bunny St intersection to Mulgrave St

Timing tbc, early 2025

Area 2 - Mulgrave St intersection

Night works complete, day works commence September 2024

Area 3 - In front of National Archives and Capital Gateway exit

To be completed next sealing season (Oct 2024 - May 2025), exact timing tbc

Area 4 - Pipitea Marae to Resene building

Most works complete. Raised safety platform and bus stop to be installed late 2024

Area 5 - Resene building to Davis St

To be completed next sealing season (Oct 2024 - May 2025), exact timing tbc

Area 6 - Davis St to Sebel Hotel

Night works commence September 2024 for approx. 6 weeks. Day works commence November 2024

Area 7 - Sebel Hotel to Wattyl Paints

To be completed next sealing season (Oct 2024 - May 2025), exact timing tbc

Area 8 - Wattyl Paints to Carpet Court

Night works complete. Day works to be complete October 2024

Area 9 - Curtain Studio to Ramset

Most works complete. Remainder expected to finish October/November 2024

Area 10 - Ramset to Tinakori Rd

To be completed next sealing season (Oct 2024 - May 2025), exact timing tbc

Area 11 - Tinakori Rd intersection

Night works currently underway. Day works scheduled to start October 2024

Area 12 - Sar St to NZCT

To be completed next sealing season (Oct 2024 - May 2025), exact timing tbc

Area 13 - Gun City

Works currently underway. Expected to be complete October 2024.

In June 2025, we will be installing cycleway separators in Areas 1 - 11.